Rigid pond liners are sold in a variety of shapes. Because the hole you dig must be an accurate match for the liner, the installation will be easier if you choose a symmetrically shaped liner.
-
To mark out the shape of a symmetrical liner, turn the liner upside down and mark around it using sand.
-
To mark out the shape of an asymmetrical liner, place it on the ground the correct way up. Use canes to keep the liner stable and to indicate its outline. Do not be tempted to turn it upside-down to make it easier to mark out, as this will produce a mirror image of the pond.
-
Remove the liner, and with a spade make cuts in the turf around your sand outline.
-
Liners are constructed with two or more shelves. Excavate only as deep as the shallow marginal shelf.
-
Using a spirit level placed on a plank, check that the edges of the shelf are level.
-
Place the liner in the hole, the right way up, and mark around the base (the deepest part of the pond) using sand.
-
Remove the liner and cut around the sand outline with a spade.
-
Dig a hole of sufficient depth to accommodate the deepest part of the liner, removing stones and debris.
-
If the ground is very stony, it is a good idea to dig the hole 50mm (2in) deeper to allow for a layer of sand to provide an even base for the liner.
-
Make sure the liner fits in the hole, removing more soil if necessary. Use a spirit level on the edges of the liner to check that it's level in all directions.
-
Start to slowly fill the liner with water. As it fills it will settle under the weight of the water. Again check that the liner is level and adjust its position if necessary before it fills too much.
-
As the liner fills up with water, backfill soil or sand into any gaps around the edges.
-
To create a neat finish paving slabs can be laid around the pond. First spread 100mm (4in) of hardcore or gravel, and compact it firmly.
-
Using a mortar mix (1 cement 4 sharp sand) bed each slab on top of the hardcore with the edges of the slabs slightly overhanging the pond. Tap each one into position with a mallet and frequently check that they are level.
-
When all the slabs have been laid, carefully fill the joints with mortar using a trowel.
|
As the liner fills with water, backfill soil or sand into any gaps around the edges.
Bed each slab on top of the hardcore with the edges of the slabs overhanging the pond and tap each one into position, checking they are level.
|